Posted inMachinery

Mammoet completes lifting of five major components at Visakh Refinery Modernisation Project in India

Mammoet completes lifting of five major components at Visakh Refinery Modernisation Project in India
Mammoet completes lifting of five major components at Visakh Refinery Modernisation Project in India

Mammoet lifted the five components at three different lifting positions: two columns at the crude distillation unit (CDU) and vacuum distillation unit (VDU), followed by three reactors and other lighter columns at the full-conversion hydro-cracker unit (FCHCU). The Stage 1 reactor at the FCHCU area weighs 1,646 Ton, making it the heaviest reactor ever installed in India.

Owned by a state-owned company Hindustan Petroleum Corporation Limited (HPCL), the project entails modernisation and enhancement of its refining capacity from 8.33MMTPA to 15MMTPA at a new process area on the east of its original plant.

L&T Hydrocarbon Engineering, the biggest engineering, procurement and construction (EPC) contractor in India engaged Mammoet’s MSG 80 ring crane, which has a 3,000 Ton lifting capacity and the ability to lift several items from a single position, due to its height. Unlike a gantry system, the MSG 80 does not need a concrete foundation.

With support from L&T, Mammoet took the modularised transport approach by moving the crane in big blocks to expedite the two relocation activities.

Another lifting solution employed at the site was a 2,000T capacity tailing frame mounted on a self-propelled module transporter (SPMT). For lifting of the Stage 1 reactor, none of the cranes on site had a sufficient lifting capacity to function as a tailing crane for MSG80. Bringing in a heavy-duty crane just for one lift was not an economical solution on top of the fact that the site was a highly congested area with no practical space to place such a large tailing crane. The in-house designed tailing frame on SPMT eliminated the need of a heavy-duty tailing crane and saved space, which improved the overall cost efficiency and productivity of the surrounding construction activity.