Project: Four Seasons Hotel
Location: Dubai
Contractor: TTS international
Scope: Lifting and installation of a glass panel with dimensions 4m x 2.6m and weight 350kg.
Solution: Two Maeda mini cranes – the MC405C and MC285 – equipped with a vacuum lifter having a maximum lifting capacity of 600kg were used to install the glass panel.
No. of operators and crew: 1 operator per machine
Job duration: 48 hours